home - Family matters
Methods of organizing construction production. The essence and basic principles of the continuous organization of construction production. Parallel method of organizing construction Method of parallel work essence and content

Rice. 38. Matrix of initial data (characteristics of object flows).

The calculation of the CPC consists of determining the possible displacement value of each subsequent object flow in relation to the previous one, based on the interests of each team (type of work), that is, based on their provision of zero stretching of the inter-object resource connection (t mrsv) and the choice of the maximum displacement between adjacent object flows, that is, calculated (t cm), eliminating the need to attract additional teams of the same type.

After determining the value of the calculated offset, it is added to the terms of the subsequent type of work and the calculation cycle is repeated. By establishing all the deadlines and duration of the complex flow, the stretching of interobject resource connections (t mrsv) and the duration of the types of work as part of the complex flow are established. The durations of object streams in the PDA are preserved.

The organization of construction production involves the following areas of scientific and industrial activity: construction organization, construction planning and construction management.

Construction organization is a system for forming or selecting a production enterprise (complex of enterprises) designed to complete a given task.

Planning is a system for linking ongoing construction and installation work in time and space, as well as a system for the supply and consumption of material and technical resources.

Management is a system for maintaining the established order or transferring construction production from one state to another with the aim of unconditionally completing the assigned task.

The construction of any building or structure of external water supply and sewerage networks and other engineering structures is associated with the production of a complex of construction processes by workers of various professions and different qualifications. Construction processes can be carried out continuously or with certain technological breaks. Thus, when laying external sewer networks with socket joints of individual pipelines, before hydraulic testing, a certain time is required for the cement mortar to harden in the socket joint. The hardening time of the solution in this complex process constitutes a technological break. Technological breaks determine more difficult conditions for organizing a continuous production process.

Construction processes can be started and completed at all sites simultaneously. In this case, the construction time of all objects will be equal to the construction time of one object, however, significant material and technical resources will be required. This method of conducting construction and installation work is called the parallel method.

The flow method of construction and installation work combines sequential and parallel methods, preserving the advantages of both methods and eliminating the disadvantages of each of them separately.

Depending on the configuration of construction projects and its influence on the organization of the flow method of construction, a distinction is made between flow-linear and flow-grabbing methods of work. The linear flow method is used in the construction of extended structures, which include external networks of water supply and sewerage systems. The flow-grabbing method is rational for the construction of buildings and structures for various purposes, with significant dimensions in height; are divided into single- and multi-tiered.

In construction, a complex flow is organized, consisting of specialized (private), object and complex flows. The products of the flows are: specialized - completed volumes of certain works; object - completed buildings and structures; complex - a group of buildings or structures.


Most production processes (not only construction) can be represented in the form of drawings, diagrams, graphs, tables, etc., which quite accurately reflect the reality of what is happening in these processes. These are models of the ongoing production process.

Flow organization of construction

If it is necessary to build several objects of the same type, then, depending on the adopted optimization criterion, the work can be organized by three methods - sequentially, parallelly and in-line.

The sequential method allows us to limit ourselves to the minimum number of workers, mechanisms, and the minimum rate of resource consumption, but it will ensure the maximum duration of work.

The parallel method, on the contrary, ensures the minimum duration of work, but it requires the maximum number of workers, mechanisms, and the maximum rate of resource consumption.

In practice, in most cases, both methods are undesirable: the first because of the long duration, the second because of the large number of workers and mechanisms. The first method is used only when the capabilities of a construction organization are extremely limited, for example, when there are large restrictions on the provision of investments. The second method is usually used in extreme conditions, when there are roads every day, for example, when eliminating accidents or the consequences of natural disasters. In most cases, the most effective is the third - in-line method. Objects (captures) are rhythmically included in the work and also rhythmically completed. Work at each site (capture) is divided into separate stages, performed by different teams.

The composition of the teams is selected in such a way that the duration of their work at each object (capture) is as equal as possible (failure to comply with this condition does not exclude the use of the flow method, but complicates it, which will be discussed below). Each team moves from object to object (from capture to capture), performing approximately the same work and preparing the work front for the team following it. The team's sequential passage of all objects (occupations) is called the work flow. A flow most often includes work of one type, for example, it could be a flow of excavation work, a flow of work on the construction of foundations, the construction of walls, the installation of floors, etc. However, it is also possible to design complex type flows, i.e. including a variety of work related to any structural element of a building or structure. Moreover, the products of a stream do not necessarily have to be individual structural elements; the stream can cover both a narrower and a wider range of work. This can be, for example, a separate process (installation of formwork, installation of reinforcement, concreting) and, on the contrary, it can be buildings or structures and even groups of buildings or structures (residential areas, drainage systems of individual farms, etc.).

Construction using the flow method involves sequential flows. An analogue of the flow method in construction is a conveyor system in a factory, but in a conveyor system products move, and the performer remains in place; in the flow method, on the contrary, performers move, but the products remain in place.

Design of continuous construction includes determining the rhythm and step of the flow, determining the number and size of teams, mechanisms, estimating the total duration of construction and the completion date of the first object (occupation). Currently, computer programs have been developed to automate the solution of such problems. They are usually included in computer-aided design systems in the form of specialized modules.

The simplest is to design rhythmic flows. With non-rhythmic flows, design becomes significantly more complicated, especially when the rhythms are not multiples of each other. In such cases, the rational solution is usually to increase the steps of the individual streams, which adapt to the variable rhythm. In these cases, teams do not arrive at the object (capture) immediately one after another, but with some breaks. During these breaks, no one works at the site (capture), but the teams themselves do not have breaks in their work.

The flow method is a method of organizing construction that ensures the systematic, rhythmic production of finished construction products based on the continuous and uniform work of work teams of the same composition, provided with timely and complete delivery of all necessary material and technical resources.

Conditions of use:

Quite a large amount of work

Dividing the construction process into stages of work

Purpose of a strict technological sequence

Use of highly specialized teams

Establishing a uniform rhythm in work.

All resources must be used constantly and continuously.

The composition and number of brigades should remain constant for a sufficiently long period of time

Stream parameters:

I. Timing parameters.

1) The total duration of work is T0.

2) The total duration of work on one gripper is TZAHV.

3) Duration of work of the team - TBR

4) Rhythms – ki

5) Technological breaks - tTECH

6) Organizational breaks - tORG.

II. Spatial parameters.

1) The work area is a part of the facility that is necessary and sufficient to accommodate workers with mechanisms and devices.

2) Plot – part of the work area allocated for a team or one worker.

3) A grip is a part of an object, a structural element on which performers of a private or specialized flow are occupied.

Min. the size of the grip is the shift productivity of the brigade.

4) Tier - part of the object obtained from vertical division according to the technical conditions of the work.

III. Technological parameters. (Number of private, special and object threads).

IV. Organization parameters.(1. Number of types of work 2. Number of pairs of threads)

V. Stat. options. (Scope of work – V, Labor-intensive – QCHDN, cost – C)

VI. Dynamic (number of workers – NPERSON, output of workers per day – Kvr, flow intensity in natural units of measurement – ​​J.

The flow can be represented graphically as a line graph or cyclogram.

The network model is depicted as a graph consisting of arrows and circles. The network diagram represents the network model with calculated timing parameters. The construction of a network is based on the concepts: work and event.

Work is a production process that requires time and material resources and leads to the achievement of certain results.

Waiting is a process that requires only time and does not consume any material resources.

Dependency – is introduced to reflect the technological and organizational relationship of work and does not require either time or resources.

An event is the fact of the completion of one or more tasks, which is necessary and sufficient for the start of the next ones.

A path is a continuous sequence of works in a network diagram.

The critical path is the complete path that has the greatest length of all complete paths.

5. Types of construction flows

I. By type of final product.

1) A private thread is an elementary construction thread consisting of one or more processes. performed by one team, unit or team. Products of a private flow are a separate type of work (for example, earthworks).

2) Specialized flow - consists of a number of particular ones, united by a single system of parameters, a flow diagram. The products of the flow are the structural parts of the building (underground part). The peculiarity is that various specialized teams can work on one grip.

3) Object flow – a set of specialized ones. Products – fully completed buildings or groups of buildings.

4) Complex flow - consists of object flows as part of industrial enterprises, complex development of microdistricts. Products – commissioned industrial. object, completed residential quarter, microdistrict.

28,29. Schedule plans in construction.

Calendar plans. Purpose and principles of development. Types of calendar plans as part of PIC and PPR

Schedule plans in construction include all planning documents in which, based on the scope of work, the sequence and timing of construction are determined.

In accordance with the construction calendar plans, supply calendar plans are developed - schedules of the need for labor and material and technical resources.

The schedule plan for the production of work on an object in the form of a linear or network schedule is intended to determine the sequence and timing of certain types of work; it is used to calculate the time requirement for labor and material and technical resources, as well as the delivery time of equipment.

Development order: 1) Drawing up a list of works 2) determine the volume of work 3) select methods for performing the main work and driving machines 4) calculate standard power and labor intensity 5) determine the composition of brigade units 6) identify the technological sequence of work 7) establish shifts of work 8) determine the duration of individual works and their combination with each other 9) compare the calculated productivity with the standard 10) based on the completed plan, develop schedules for the need for resources and their provision.

The initial data for the calendar plan in the PPR are: 1) calendar plans as part of the PIC 2) construction duration standards or directive assignments 3) technological maps for construction, installation and special works 4) working drawings and estimates 5) data on participating organizations.

Consists of 2 parts: the left one is calculated, the right one is graphical.

Estimated: 1) List of works 2) Scope of work 3) Labor intensity and machine time costs 4) Duration of work 5) Number of shifts 6) Number of workers per shift and crew composition 7) Calculation of crew composition

Design is carried out at the expense of customers, who enter into contracts for the implementation of design work with the general designer.

General designer is an organization that carries out the bulk of design work. Involves specialized design organizations to carry out individual parts of the project (research, special work, etc.) on a contractual basis. At the same time, she is responsible for the complexity of the project.

Scheduling and organization of construction of the underground part of the building

The leading process should be the installation of basement structures. Depending on the design and volume of work, they are divided into grips. It is advisable to have at least 2 grips. This allows you to break down the work and organize its continuous execution.

1) Selection of mounting mechanism. For the zero cycle, it is best to use rail-mounted or crawler-mounted cranes. The pit is excavated using an excavator with a bucket with a capacity of 0.33-0.65 m3.

2) Installation of a) prefabricated foundations is carried out simultaneously with manual removal of the soil b) Pile foundations (a multi-grip system should be adopted, optimally 6: (1) Striker, (2) cutting and preparing heads, (3) cleaning the base of the grillage, formwork and reinforcement work (4) Concreting (5) curing (6) stripping)

3) Installation and laying of basement walls and partitions.

4) Filling the sinuses of the pit from the inside and backfilling from the inside. This process is planned in schedule II for wall installation.

5) Installation of communications outlets and inputs (sewerage, water supply, heating networks, gas, electricity).

6) Waterproofing of walls, it can be shown in graphics outside the flow.

7) Installation of floors and welding work on them are planned after finishing the concrete floors in the basement.

8) Filling the sinuses from the outside.

10. Composition and content of the feasibility study

The main indicators characterizing the level of design of the organization of construction work include: duration of construction, level of mechanization of main types of work, unit costs of labor, machine time, energy resources and cost of work related to a unit of construction product (for example, labor intensity in man-days per square meter. m of building area, electricity costs kWh per cubic meter of concrete structure, average daily output in monetary terms).

The resulting feasibility studies are analyzed by comparison with the achieved indicators at similar facilities, with advanced domestic and foreign experience.

Construction methods:

Open method (completed zero loop method) i.e. foundations for the building frame are made simultaneously with foundations for equipment and shelves;

Closed method - installation of foundations for equipment and shelves after the construction of the above-ground part of the building under the roof;

Combined - simultaneous installation of building structures and shelves together with the supply and installation of equipment. One specialized thread;

Separate method - performing the installation of building structures in one specialized flow, and installation of equipment (rigging, installation and mechanical installation) - in a specialized flow in a fully constructed building;

Combined method - performing part of the equipment installation work separately from the installation of building structures in the constructed premises.

SEQUENCE OF WORK AND CONSTRUCTION OF BUILDINGS
The sequence of work is determined by the following main factors, the phased development of which ultimately leads to the implementation of the construction process:
development area;
site preparation (work of the preparatory period);
construction of the underground part;
construction of the above-ground part;
construction of enclosing structures;
installation of engineering equipment;
interior finishing works;
installation of technological equipment;
external finishing works;
landscaping.
Selecting a development area is the very first stage of construction implementation. At this stage, based on the assigned tasks, the most optimally located land plot is determined, meeting both the requirements for a rational supply of building materials, structures and resources for the construction period, and meeting the necessary operational requirements, and geotechnical surveys are carried out. They carry out state registration (examination of buildings and structures planned for the development of a given land plot), allocation of a land plot for construction and preparation of architectural and planning assignments.
Site preparation is a mandatory stage, approximately similar in scope of work for industrial and civil construction. Basically, site preparation means carrying out engineering surveys, tying the building being constructed to the ground, demolishing old buildings, relaying networks, erecting temporary buildings and structures.
The accepted sequence of work during the construction of a separate building or a complex consisting of adjacent buildings of the same type can significantly influence the overall construction period.

Let's consider one of the methods for constructing buildings or performing interrelated work - sequential.
The sequential method provides that when constructing a separate building, a team of workers completes each subsequent work only after completing the previous one. Consequently, the total duration of construction of a building is equal to the sum of the durations of individual types of work, i.e. in this case, a small number of personnel working at one facility will be required. In the case when a number of buildings of the same type will be built one after another, each subsequent building only after the completion of the previous one, then a single team of workers will erect these buildings sequentially, moving from one completed object to the next. With this method, the total duration of construction of a complex of buildings is equal to the product of the duration of construction of one house by their number, but in the same way as in the construction of an individual building, a relatively small number of workers are required, working for a long time in one place.
Sequential methods are characterized, on the one hand, by the sequence of execution of the work of the complex, and on the other, by the absence of simultaneity in their implementation.
The need for their use is determined:
specifics of production;
design features of structures;
technology of work;
safety precautions.
Advantages of the method:
simplicity of its organization;
low sensitivity to changes and even abandonment of the rhythm of work;
a high degree of alternativeness of the chain (sequence of work), since its nature can be quite freely changed at any time (Fig. 3.).
Disadvantages of the method:
The long duration of a set of works is maximum compared to other methods with equal intensity of work;
The great need for resources is maximum compared to other methods with the same deadline for completing a set of works.
As a result of these shortcomings, sequential methods of organizing work as independent ones are used very rarely, except in cases where these methods are the only ones possible (pipes, masts, towers, cooling towers, etc.).

Work production schedule
With the sequential method, all technological cycles are carried out first on the first gripper, then on the second, etc.
The transition to the next occupation is carried out after completion of work on the previous one.
T = t × m
T is the total duration of work, t is the duration of work on one grip; m – number of grips
A team of workers will move sequentially from job to job, requiring a small number of personnel working at one site.
Q = T × n, (person days)
Q is the total labor intensity, T is the total duration, n is the number of people.
Diagram of labor movement
After constructing a calendar schedule and determining the construction period, they begin to construct a diagram of the movement of labor, which serves to determine the need for human resources and the need to provide them with the appropriate volume of household services, temporary buildings and structures, required equipment, personal protective equipment, and so on.
The diagram displays the number of workers on the construction site (vertical scale) at any point in time (horizontal scale) throughout the entire construction period.
As a rule, the resulting diagram of the movement of workers does not look entirely successful: there are peaks and valleys - sharp (by more than 30%) short-term (several days) changes in values. To ensure a more uniform workload of work crews, the diagram is optimized based on the following requirements:
1. As the scope of work unfolds, the total number of workers on the construction site should increase, then gradually decrease.
2. The value of the coefficient of uneven movement of workers (the maximum number of workers on the site, determined by the diagram, divided by the average number of workers, determined by dividing the area of ​​the diagram by the length of its base) should tend to 1.5.

Parallel-flow methods of organizing work (parallel flows) are a more general case of the formation and calculation of flows. They are usually used when individual flow methods do not give the required results (even when using the reviewed methods for optimizing them). Therefore, the formation and calculation of parallel-flow methods are carried out after the formation and calculation of individual-flow methods. This raises questions: what types of work or work should additional teams be assigned to and how to distribute work between teams of the same type?

A.V. Afanasyev proposed assigning additional teams of the same type to the longest types of work in a quantity that ensures a reduction in their duration to the required value, distributing work between teams of the same type during the flow calculation with critical work identified taking into account resource and frontal connections, distributing work in in accordance with the initial priority with priority loading (with equal opportunities) of the most powerful brigades, and with equal power of brigades - those of them that have the lowest serial number. If there are teams of the same type of different capacities, he recommends placing them on a matrix (in the ODF system) in descending order of capacity.

A number of researchers have proposed modifications of this algorithm, namely, loading brigades not in accordance with the initial order, but selectively, as fronts are released, loading brigades not in accordance with their capacity, but in accordance with the queue awaiting loading or in accordance with the possibility of an earlier completion of work. These modifications in certain cases give better results, but not always. All possibilities for the formation of parallel-flow methods, taking into account the specified modifications, as well as according to a fundamentally different (also proposed by A.V. Afanasyev) method of oriented assignment of additional teams to work that restrains the compaction of flows, are considered in a special course, and in this main course - only first method.

Let us illustrate this method of forming and calculating the parallel-flow organization of work using an example.

Let the same conditions as above be given, and a flow with critical jobs identified taking into account resource and frontal connections be formed and calculated. The resulting flow duration is 40 units. time, does not satisfy. It is necessary to reduce it to 35 units. time due to the introduction of additional teams of the same type.

Consideration of the parameters of an individual flow (initial data) shows that types of work have different durations and in order to reduce the duration of types of work “A”, “B” and “D” to the minimum corresponding to type “B”, that is, to reduce the irregular flow To achieve a harmonious look, it is necessary to introduce additional teams, one for types of work “A” and “D”, and two teams for types of work “B”. The involvement of such additional brigades turned out to be possible, but additional A 2, B 2, B 3 had less power than A 1 and B 1, and brigade G 2 had equal power with G 1 (A 2 = 0.5 A 1; B 2 = 0.5 V 1; V 3 = 0.3 V 1; G 2 = G 1).

We will carry out the formation and calculation of a parallel-flow method of organizing work.

OFR Types of jobs Types of work and team indices
A B IN G A 1 A 2 B IN 1 AT 2 AT 3 G 1 G 2
Work fronts 0 4 4 6 6 13 13 18 0 4 4 6 6 13 13 18
I
4 9 9 12 13 22 22 28 0 10 10 13 13 22 22 28
II
9 12 12 14 22 30 30 33 4 7 13 15 15 31 31 34
III
12 16 16 19 30 36 36 40 7 11 15 18 18 36 36 40
IV
Σt j
n additional brig. - Power A 2 =0.5 A 1, V 2 =0.5 V 1, V 3 =0.3 V 1, G 1 =G 2

Rice. 34. Matrix with the results of the formation and calculation of a parallel flow with the CR at early deadlines for completing work.

Consideration of the calculation results shows that the inclusion of three additional teams in the flow (no work was found for team G 2) did not produce any positive effect. This happened because brigades A 2, B 2 and B 3 had little power.

Indeed, if, instead of these brigades, brigade B 2 with the capacity of brigade B 1 is included in the flow, then the required reduction in duration will be achieved.

OFR Types of work and team indices Ordinal numbers
A B IN 1 AT 2 G 5 10 15 20 25 30 35 T i
Work fronts 0 4 4 6 6 13 13 18
I
4 9 9 12 12 21 21 27
II
9 12 12 14 14 22 27 30
III
12 16 16 19 21 27 30 34
IV
T j

Rice. 35. Parallel flow with the Kyrgyz Republic when work is completed early.

Based on this, formed as a rational structure of a parallel flow with critical works identified taking into account resource and frontal connections, parallel flows with research work and with the NOF can be calculated.

OFR Types of work and team indices T i Ordinal numbers
A B IN 1 AT 2 G 5 10 15 20 25 30 35
Work fronts 0 4 9 11 11 18 18 23
I
4 9 11 14 14 23 23 29
II
9 12 19 16 18 26 29 32
III
12 16 16 19 23 29 32 36
IV
T j The reader is advised to draw a calendar chart

Rice. 36. Parallel flow with research

OFR Types of work and team indices T i Ordinal numbers
A B IN 1 AT 2 G 5 10 15 20 25 30 35
Work fronts 0 4 4 6 6 13 13 18
I
4 9 9 12 12 21 21 27
II
14 17 17 19 19 27 27 30
III
17 21 21 24 24 30 30 34
IV
T j The reader is advised to draw a calendar chart

Rice. 37. Parallel flow with NOF

It is of undoubted interest to compare the varieties of parallel flow.

Table 2

Parameters of work organization options

Method index T Duration of types of work Front duration. complexes
A B IN 1 AT 2 G I II III IV G
PP with KR
PP with research
PP with NOF

A formal summation of the parameters for each method shows that the most preferable is a parallel flow with critical work identified taking into account resource and frontal connections (with early deadlines for completing work).

However, this approach does not take into account the economic side of the matter, that is, the costs of increasing the duration of each type of work and each frontal set of works and the entire parallel flow as a whole are not taken into account. All this must be taken into account in real conditions.

In conclusion, considering the issue of forming and calculating parallel flows, it should be noted that their duration depends on the sequence of development of work fronts. Therefore, a search must be made for optimal queues that provide the minimum duration. Corresponding directed search algorithms have been developed and are discussed in a special course.

LECTURE No. 8

COMPARISON OF WORK ORGANIZATION OPTIONS.

A modern approach to organizing work requires the development of all competitive options.

Complex flows can be formed:

In the form of combined streams with full preservation of the structure of previously developed object streams;

In the form of aggregated flows, which ensure the immediate start of work by teams in the subsequent object flow after completion of work in the previous one, but at the same time the structure of the object flows changes;

In the form of compacted ones, which ensure the minimum duration of the entire complex stream, but at the same time the structure of the original object streams changes.

The initial data when forming complex flows are presented in the form of parameters of independently generated object flows, presented on matrices in the ODF system. Complex combined flows (CFC) are formed by identifying possible periods of displacement of the subsequent object flow relative to the previous one, based on the interests of the continuous work of each team. In this case, the maximum is taken as the calculated one, eliminating the need for additional teams of the same type. The total duration of the PDA is defined as the sum of all calculated offsets between adjacent object streams and the duration of the last object stream.

A complex aggregated flow (CAF) is formed by identifying the estimated periods for the deployment of types of work, taking into account the parameters of all object flows. In this case, the structure of object streams is destroyed. The total duration of the CPA is determined as the sum of the deployment periods of types of work and the duration of all works of the last type as part of a complex flow.

A complex compacted flow (CPF) is formed by preserving the structure of the first object flow in the queue and ensuring the continuous execution of all work of the first type as part of the complex flow. The timing of other types of work of object flows as part of a complex flow is determined by the availability of resources and work areas. They can be early or late. In this case, if the early and late deadlines coincide, the corresponding type of work of the object flow is critical. The sum of critical jobs that make up one chain (single-critical path) determines the duration of the CPU.

Let us illustrate the application of this method for calculating complex flows with an example.

Initial data in the form of timing of work types of object flows, duration of work types (t ij) and possible combination of adjacent types (tc) are presented on the M-1 matrix (in the ODF system). Strictly speaking, this information is redundant, since the object flow unambiguously determines either the timing of types of work, or their duration and combination, but when calculating complex flows without a computer, it is convenient to use one in one case, and another in another case.

M-1
A tc B tc IN tc G
I 0-16 9-19 11-41 27-45
t Ij
II 0-30 15-40 25-35 35-60
t IIj
III 0-20 18-30 25-45 30-50
tIIIj
IV 0-30 20-45 40-65 55-70
t IVj
M-2 A B IN G Ti M-3 A B IN G Ti
I 0-16 9-19 11-41 27-45 I 0-16 9-19 11-41 27-45
t cmj max 16 t mcrv
II 0-30 15-40 25-50 35-60 II 16-46 31-56 41-66 51-76
t cmj max 30 t mcrv
III 0-20 18-30 25-45 30-50 III 46-66 64-76 71-91 76-96
t cmj -5 max 20 t mcrv
IV 0-30 20-45 40-65 55-70 IV 66-96 86-111 106-131 121-136
Σt сij T j

Rice. 39. Matrices of displacements (M-2) and results of calculation of the CPC (M-3)

The calculation of the CPA consists of determining the possible value of the deployment period for each subsequent type of work in relation to the beginning of the previous one in relation to each front (T p ij) and choosing the maximum (calculated) one, which excludes the premature start of the subsequent type of work on any front.

Various methods have been proposed for determining the estimated value of the deployment period, including those by Aguilar and Mena. In this case, the sum of the durations of the 1, ..., i-th works of the type preceding the j-th under consideration is determined, minus the calculated value of the combination on the i-th front (j-1) and the j-th types of work and the sum of 1, ..., (i -1)-th works of the type under consideration on previous fronts.

After determining the estimated periods for the deployment of the second and subsequent types of work, the timing of the implementation of object types of work as part of a complex flow and its duration, as well as the extension of frontal connections (t fsv), are determined as the difference between the start of work ij and the end of work i(j-1) in minus the calculated combination of adjacent types of work of the object flow (t c).

M-4 A t frsv B t frsv IN t frsv G Ti
t s t s t s
0 16 39 49 41 71 68 86
I
t mrsv
16 46 49 74 71 96 86 111
II
t mrsv
46 66 74 86 96 116 111 131
III
t mrsv
66 96 86 111 116 141 131 146
IV
T p j
T j

Rice. 40. Matrix with the results of calculating the KPA.

T r B1 = 16 – 7 – 0 = 9; T r B1I = (16 + 30) – 15 – 10 = 21;

T r B1II = (16+30+20) – 2 – (25 + 10) = 29; T r B1V = (16+30+20+30)–10–(12+25+10)=39.

calc. T r B = 39

T r B1 = 10 – 8 – 0 = 2; T r B1I = (10 + 25) – 15 – 30 = -10;

T r B1II = (10+25+12) – 5 – (25 + 30) = -13; T r B1V = (10+25+12+25)–5–(20+25+30)= -8.

calc. T r B = 2

T r G1 = 30 – 14 – 0 = 16; T r G1I = (30+ 25) – 14 – 18 = 23;

T r G1II = (30+25+20) – 15 – (25 + 18) = 17; T r G1V =(30+25-20-25) –10–(20+25+18)=27.

calc. T r G = 27

Calculation of the CPU consists of determining the deadlines for completing work types of object flows as part of a complex flow, provided that the deadlines for completing work types of the first (in queue) object flow are preserved and the continuous execution of work of the first type (with zero stretching of inter-object resource connections) as part of a complex flow. The timing of the remaining types of work of object flows as part of the complex is determined sequentially as resources and fronts are released, with mandatory consideration of the possible combination of related types of work.

M-5 A t frsv B t frsv IN t frsv G Ti
t s t s t s
0 16 9 19 11 41 27 45
I
t mrsv
16 46 31 56 41 66 61 86
II
t mrsv
46 66 64 76 71 91 86 106
III
t mrsv
66 96 86 111 106 131 121 136
IV
T j

Rice. 41. Matrix with the results of calculating the efficiency factor.

The calculations of the KPC, KPA and KPU showed that these options for organizing a complex flow are characterized by different parameters.

Table 3

Complex Flow Option Options

A formal summation of the parameters for each method shows that the most preferable is the complex flow combined. However, this approach does not take into account the economic side of the matter, that is, the costs of increasing the duration of each type of work and each object flow and the entire complex flow as a whole are not taken into account, as well as the efficiency of the object flows themselves. All this must be taken into account in real conditions.

In conclusion, considering the issue of formation and calculation of complex flows, it should be noted that their duration depends on the order in which object flows are entered into the complex flow. Therefore, a search must be made for optimal queues that provide the minimum duration. Corresponding directed search algorithms have been developed and are discussed in a special course.

Comparison of work organization options

A modern approach to the organization of work, in particular, the St. Petersburg school of continuous work organization, requires the development of all competitive options for their assessment and selection of the most effective, that is, the most appropriate to the specific production conditions. Options for organizing work can be assessed according to one or another criteria.

A criterion (gr. kriterioh) is a “touchstone”, a distinctive feature, a measure. When assessing options for organizing work, various individual criteria can be used (taking into account their priorities) and differential ones, combined (taking into account their significance) into an integral one. .

Individual criteria are presented, as a rule, in absolute terms (in terms of cost, time, labor costs and other natural indicators). The choice of the best option when using individual criteria is significantly influenced by the order of their application, determined by the significance (priority) of each of them. In this case, different systems for using individual indicators are possible (without limiting the discarded options that are less effective than those selected according to the criterion under consideration or with a restriction that allows the use of all criteria, as well as by distributing the compared options for each criterion (according to their corresponding places), summing up the place numbers and recognition as the best option with the lowest score). If it is necessary to strengthen the significance of certain criteria, their significance coefficients are introduced (the numbers that determine the places occupied by the option according to the relevant criteria are multiplied by the significance coefficients).

Differential criteria are always presented in relative values, limited by a certain limit (from 0 to 1, from 0 to 6, from 0 to 10, etc.). They are combined, taking into account the significance coefficients, into an integral one. In this case, significance coefficients are set (accepted) by developers or a higher level of management, taking into account specific production conditions and a more general one in relation to the problem under consideration. There is no (sufficiently strict) methodology for assigning significance coefficients (for example, it is impossible to strictly determine how much more important it is to build an object in a shorter time or cheaper), but experience allows us to assign coefficients, and if the assignment is unsuccessful, to correct them.

The lecturer proposed the following as differential criteria:

1. Timeliness of work (K 1). The criterion characterizes the deviation of the planned duration of work from the specified one, which in most cases causes a disruption in the organization of a wider range of work.

K 1 = T D / T, if T D< Т

K 1 = T / T D, if T D > T

where T is the planned duration of the work package;

T D – directive (normative) duration of the work package.

2. Correspondence between the need for resources and their availability (K 2). The criterion characterizes and largely predetermines the feasibility of the work organization option.

K 2 i = R Hi / R ni if ​​R Hi< R ni

K 2 i = R ni / R Hi if R Hi > R ni

K 2 = Σ K 2i П i / П

where K 2i is the criterion for compliance of the i-th type of resource;

P i – labor intensity or cost of the i-th type of work, or the cost of the i-th type of resources;

P – total labor intensity or cost of the entire complex of work, or the total cost of all resources;

m – number of types of resources.

3. Efficiency of resource use (K 3). The criterion characterizes the stability of resource use, that is, the degree of duration of certain types of work (t i) in the overall complex (taking into account their labor intensity or cost).

K 3 = Σ (t i / T) (P i / P)

4. Time combination of different types of work (K 4). The criterion characterizes the degree of flow of the work organization option.

K 4 = 1 – T / Σ t i

5. Continuity of resource use (K 5). The criterion characterizes the degree of uninterrupted work (within each individual type of K 5 i and K 5 as a whole).

The presence of downtime of resources is undesirable, since it leads to an increase in the cost of construction of the facility, but it is inherent in some methods of organizing work (with NOF, with KR, with organizing work on tours).

K 5 i = t N i / t i ;

K 5 = Σ K 5i П i / П

where t Hi is the duration of the i-th type of work during its continuous execution;

t i is the planned duration of the i-th type of work.

6. Uniformity of resource use (K 6). The criterion characterizes the stability of the use over time of individual types of resources (types of work) and the entire complex.

K 6 i = 1 – f i / F i

K 6 = Σ K 6i П i / П

where f i is the total area protruding above the line of uniform consumption over time of the i-th resource;

F i – total area characterizing the consumption of the i-th resource over time.

7. Criticality of work (K 7). The criterion characterizes the degree of criticality of work within each type (K 7 i) and as a whole (the entire complex).

K 7 i = P k r i / P i

K 7 = Σ K 7i P i / P = Σ P kpi / P i

P kр i – labor intensity or cost of critical work as part of the i-th type;

P – labor intensity or cost of the entire complex of work.

8. Continuity of development of work fronts (K 8). The criterion characterizes the lack of downtime in work within the frontal complexes (K 8 j) and in general (across all frontal complexes). The presence of downtime in work fronts is undesirable, since it leads to freezing of working capital, but it is inherent in some methods of organizing work (with research work, with the Kyrgyz Republic, with the organization of work on tours).

K 8 i = t Hj / t j ;

K 8 = Σ K 8j P j / P

where t Hj is the duration of the j-th frontal set of works during their continuous execution;

t j is the planned duration of the j-th frontal set of works;

P j – labor intensity or cost of the j-th frontal set of works;

n – number of frontal complexes (fronts) of work.

9. Saturation of work fronts with resources (K 9). The criterion characterizes the degree of use of work fronts during production (normal, that is, providing normal working conditions for performers; not completely saturated with performers; oversaturated with performers, worsening the working conditions of everyone, but increasing the total volume of production; extremely saturated, that is, not providing further saturation of the front works performed by performers have no positive effect.

K 9 i = R opt i / R i if R opt i< R i ;

K 9 i = R i / R opt i, if R opt i > R i;

K 9 = Σ K 9i П i / П

where R opt i is the optimal composition of performers of the i type of work;

R i is the planned composition of performers of the i-th type of work.

10. Efficiency of resource use and development of work fronts (K 10). This aggregate criterion proposed by A.V. Afanasyev allows one to simultaneously take into account the influence of two alternative factors. If necessary, significance coefficients can be introduced into the criteria, establishing the relationship between the efficiency of resource use and the development of work fronts:

K 10 = (K 5 + K 8) / 2

With different significance of downtime of resources and work areas:

K 10 = (Z 5 K 5 + Z 8 K 8) (Z 5 + Z 8),

where Z 5 is the significance of resource downtime, Z 8 is the significance of work front downtime.

11. Efficiency of dynamics of capital investments (investments). The criterion was proposed by the lecturer together with V.Z. Velichkin and V.I. Vtyurin and characterizes the degree of rationality of the dynamics of capital investments determined by the planned organization of work.

When forming the criterion, it is accepted that before investing funds (in the form of performing any work, manufacturing any structure, installing any equipment), they are in circulation and provide income (according to the accepted rate of efficiency), and after investment of income do not bring, that is, there is a loss (corresponding to the efficiency norm). The total effect of the i-th capital investment is determined by the difference between income and loss (calculated using the compound interest formula). The overall absolute effect is determined by the sum of the effects of all capital investments, and the relative indicator is defined as the ratio of the sum of the maximum possible loss and the achieved efficiency to the base, that is, the sum of the maximum possible income and the maximum possible loss.

Let the i-th capital investment take place at time t i (K t i). At the same time 0< t i < T, а нормативный коэффициент эффективности Е Н.

Then after 1 year, through capital investment, its value will increase:

K ti+1 = K ti + E H K ti = K ti (1 + E H)

After 2 years, its value (at compound interest) will increase:

K ti+2 = K ti+1 + E H K ti+1 = K ti+1 (1 + E H) = K ti (1 + E H) 2

After 3 years, its value (at compound interest) will increase:

K ti+3 = K ti+2 + E H K ti+2 = K ti+2 (1 + E H) = K ti (1 + E H) 3

After the period T – t i (before the facility is put into operation), its value will increase:

K T- ti = K ti (1 + E H) T-ti

In accordance with this, the amount of loss from the diversion of Kt i from circulation for the period T – t i will be determined equal to

Y Kti = K ti (1 + E H) T-ti – K ti = K ti [(1 + E H) T-ti – 1]

However, until the moment of investment, this amount of funds was in the national economic circulation and brought a certain income. Bringing the capital investment K ti to the start of construction is determined by the value K 0i.

Using the above formula:

K ti = K oi (1 + E H) ti

can be determined (by compound interest) K oi

K oi = K ti

In accordance with this, the amount of income from the presence of K ti in the national economic turnover will be determined equal to:

D k+i = K ti – K oi = K ti – K ti= Kti

(1 + E H) ti (1 + E H) ti

The total value of the effect from the i-th capital investment is determined as the difference between the income and loss values:

E Kti = D Kti –U Kti = K ti – K ti [(1+ E H) T-ti –1] = K ti

(1 + E H) ti (1 + E H) ti

To ensure brevity, you can enter the notation

a = (1 + E H) ti

E Kti = K ti

The total value of the effect from all capital investments during the entire period of construction is determined equal to:

E K = S K ti

where n is the number of capital investments.

In accordance with the accepted system of differential criteria, this criterion must be presented in the form of a relative value. This can be achieved by calculating the total economic effect relative to zero (on the graph), that is, by adding its value to the maximum possible loss (investing all funds on the first day of construction), and by relating this amount to the value of the base, that is, to the sum of the maximum income and the maximum loss.

Maximum income from the entire amount of investment (D K)

max D K = K (1 - b T)

Maximum loss from the entire investment amount (U K)

max U K = K (a T - 1)

Base size:

B = max D K + max U K = K (1 - b T) + K (a T - 1) = K (a T - b T)

K 11 = max U K + E K = K (a T - 1) + S K ti (2 - b ti - a T-ti)

B K (a T - b T)

It is easy to verify that when all investments are made at the start of construction (t 1 = 0), the numerator is equal to zero, and, accordingly, K 11 = 0.

When making all investments at the time of completion of construction, that is, when purchasing an object built without intermediate payment of costs (t i = T), the numerator is equal to the base and, accordingly, K 11 = 1.

12. Efficiency of duration (term) of work (K 12). The criterion characterizes the positive effect of reducing the duration of work.

K 12 = 1 / (1 – E N) T

The considered differential criteria for the quality of work organization are reduced to an integral one:

where Z i is the significance coefficient of the i-th criterion (specified)

n – number of differential criteria defined and taken into account.

It was noted above that the significance coefficients are set taking into account the specific conditions of work and the solution of a more general (in relation to the problem under consideration) problem. It should be added to this that at least one significance coefficient (from the entire set) must be equal to one (the rest may have a larger value), and the coefficients for alternative and, above all, criteria opposite in the direction of influence must be different, that is take into account the real requirements for the organization of construction and the conditions of work (for example, K 1 and K 12, K 2 and K 3, K 4 and K 6).

In conclusion, considering the methodology for comparing options, it should be noted that any integral criterion for assessing quality, including coefficients of significance of individual or differential criteria, is a measure of quality only in relation to the considered options for organizing work, which are in the same conditions. When conditions and, accordingly, significance coefficients change, the same options for organizing work will have different indicators of integral criteria.

SEQUENTIAL AND PARALLEL METHODS OF ORGANIZING CONSTRUCTION PRODUCTION


With a sequential method of organizing construction production, there is significant downtime of machines and loss of time associated with moving them from one place to another. Frequent changes in types of materials, products and structures lead to significant difficulties in the work of manufacturing enterprises, transport and supply authorities.

The construction technology of the facility reflects the fundamental features of the applied production methods and organization of the entire complex of construction and installation works. The concept of production technology for any type of work includes not only the content and sequence of the production process, but also the possibility of combining individual works or operations in time. The basic rules for construction and installation work are determined by SNiP and industry instructions and recommendations.

Modern methods of organizing socialist construction production are divided into sequential, parallel and continuous.

In our country, by decision of the USSR government, capital construction without approved projects and estimates is prohibited. The latter must be economical and reflect advanced domestic and foreign experience. The decisions of the XXVII Congress of the CPSU note that it is necessary to use economical space-planning solutions, structures, materials, advanced methods of organizing production and labor, consistently reducing the consumption of material, fuel, energy and labor resources per unit of production. On this basis, implement a reduction in the specific indicators of the estimated cost of construction in construction projects of the twelfth five-year plan, including construction and installation work by an average of 4-5% in the national economy.

For the first time in domestic practice, the flow method was used in 1949 on the construction of the Dashava-Kiev-Bryansk-Moscow gas pipeline. In 1953 Temporary technological rules (instructions) for the production of work during the construction of the linear part of main steel pipelines were approved, in which, as the most important condition for performing construction work in a short time, the organization of continuous execution in a certain technological sequence of all types of construction and installation and welding work simultaneously on all linear lines was put forward sections of the route.

Model material value. A random, unjustified choice of material can not only hinder the development and practical application of a new method or limit its capabilities, but also fundamentally distort its essence. Here is one of the most striking examples of this, which has already become a household word in the history of breadboard model design. At the Leningrad Lengiprogaz Institute, the first organization in our country to use mock-ups in the design of petrochemical production facilities, a generally correct understanding of the role of the mock-up in design and construction was found. The model was accepted as a design tool, and it was also sent to the construction site for use as design documentation for the installation of the pipeline part of the facility. Taking into account possible conditions of transportation and operation at the construction site that are severe for the design of the model, the value of its strength was also consistently correctly assessed. And yet, a serious mistake was made - excessive emphasis on strength to the detriment of other required qualities of the models. The model literally became iron; almost all of its elements were made of metal. During the assembly process, the models were connected to each other by soldering. Naturally, there was no talk about any detachability of connections and

The main parts of the enterprise project are technological, construction and technical and economic. Technological part of the project contains decisions on the organization of production, technology, process and selection of equipment that determine the capacity of the enterprise, as well as methods of mechanization and automation of production. The construction part determines the nature and type of buildings and structures, their space-planning and design solutions. Part of the project Construction organization establishes the volume of construction and installation work for each facility, the sequence and timing of construction and methods for performing basic work, and also identifies the need for basic construction materials and parts, construction machines, vehicles and workers. In technical and economic. parts, the choice of construction site is justified, the basic technical and economic are established. indicators of the designed enterprise, characterizing economic. effectiveness of adopted design decisions. An integral part of the project is

The flow method is a progressive method of organizing construction production. The essence of the flow method is to organize sequential, continuous and rhythmic production of construction work, which makes it possible to effectively use material and labor resources. The flow involves producing certain volumes of construction products at equal intervals and increasing the profitability of construction. Experience shows that when switching to " flow"Construction duration is reduced by an average of 20%, labor productivity increases by 8-10%.

With the flow method of organizing construction the construction process is divided into separate components and operations, the implementation of which is entrusted to separate integrated teams or specialized units. These teams or units move evenly from one occupation site to another along the entire work front, and at each site construction processes are sequentially carried out in strict accordance with their technological order. Each team, finishing work on its assigned area, prepares the area for a new cycle of work to be performed by the next team.

At each site, work cycles follow in the established order, which allows for maximum combination of work in time, performing them at the pace provided for by the construction and installation work schedule.

Uniform movement of workers from one grip to another is possible only if the number of workers in teams and units remains constant, and the grips are equal in labor intensity to the work performed.

When organizing construction using the continuous method, the construction of a building is usually divided into the following cycles: preparatory, zero, construction of the above-ground part, finishing work.

The flow method is complemented industrialization of construction, i.e., the continuous transformation of the construction process into a mechanized process of continuous assembly of buildings and structures from factory-made structures.

In construction practice, for planning and managing construction flows, construction processes are modeled using their graphical representation: line graphs and network graphs are developed.

In accordance with the Instructions for the development of projects for the organization of construction and production of works for the construction of complex facilities, enlarged network diagrams are drawn up. This need is explained by the presence of complex relationships between individual units and the farms that serve them.

Network diagrams are a graphic reflection of construction technology. A distinctive feature of a network diagram is a clear relationship between activities with a strict technological sequence of their implementation.

Each network diagram has a starting event (the start of work), intermediate events (the fact of the completion of one or more works), and an ending event. Each “event” occurs at a certain point in time and is indicated on the graph by circles and a serial number. Between events there is a process of work that requires an investment of time and resources. Activities on the network diagram are indicated by arrows, and their duration (in days) is indicated under the arrow.

All intermediate events and related work are located on the network diagram between the initial and final events in accordance with the order of their implementation: some of them are technologically dependent, others are independent, i.e., they can be executed in parallel.

It should be noted that there are two more types of connections between events: " expectation" requiring only time (e.g. drying plaster, curing concrete), and " addiction", which requires neither time nor resources, but only compliance with consistency in the execution of work. Expectation is indicated on the graph in the same way as work - with a solid line, dependence - with a dotted line.

The change of events that are interconnected by work recorded on the graph is called " by". The network of paths diverges from the initial event and converges to the final event. The duration of each path is determined by summing the duration " lying"works on it. The longest path in time between the initial and final events, which determines the completion date of the construction of the object, is called the critical path.

The figure shows, as an example, a fragment of a network diagram for the construction of a one-story warehouse building. The building is divided into three sections. Excavation work, installation of monolithic foundations, delivery and preparation of prefabricated elements for installation, and installation of structures are carried out on parallel streams.

According to the schedule, the main work on the installation of structures (event 7) can begin after the completion of preparatory work 1-2, as well as excerpts of foundation pits on the first block 2-4, installation of monolithic foundations 4-6 and completion of concrete hardening in foundations 6-7. Work 6-7 is actually an expectation, since the process of hardening concrete in foundations requires little resources, but this requires a certain time for the strength of concrete to increase. In addition, the start of installation (event 7) can begin after completion of work 1-3, i.e., delivery and installation of the crane for laying out elements and 3-5 - laying out and preparing for installation of structures on the first grip. Jobs 5-7 and 9-11 are dependencies.

The name and composition of the works shown in the network diagram (Fig. 14.1), their duration in days are indicated in the table. 14.1.

The duration of the paths for the work outlined on the network diagram is calculated in table. 14.2.


The longest, i.e., critical path, will be path No. 1, lasting 122 days. This “path” determines the duration of the entire complex of work on the construction of the building.

Calculation of the critical path allows you to compare the total duration of construction work with a given period or with the standard construction duration. If the “critical path” turns out to be longer than provided for by construction duration standards, then reserves can be used to reduce the overall construction period due to non-critical work. In this case, the duration of “non-critical” work is extended within the identified time reserves, and the released resources are used to speed up work on the “critical path”.

 


Read:



Buckwheat porridge recipes

Buckwheat porridge recipes

On water so that it turns out crumbly and very tasty? This question is of particular interest to those who like to consume such lean and healthy...

Affirmations for material well-being

Affirmations for material well-being

In this article we will look at two main areas of affirmations for financial success, good luck and prosperity. The first direction of money affirmations...

Oatmeal with milk, how to cook oatmeal with pumpkin (recipe)

Oatmeal with milk, how to cook oatmeal with pumpkin (recipe)

When the topic of oatmeal comes up, many of us sigh with sadness and hopelessness. Meanwhile, it is well known that this is a traditional food of the English...

Education and formation of conditioned reflexes

Education and formation of conditioned reflexes

“Nervous system” - The midbrain is well developed. The improvement of the nervous system also affected the development of sensory organs. Nervous system of fish...

feed-image RSS